Stage two South West Rail Link
edmondson park station construction site in june 2012
leppington station entrance in february 2015
stage 2 included extending railway line westward towards leppington. involved:
a rail flyover on south side of glenfield station take new line on main south line , southern sydney freight line.
11.4 kilometres of double track glenfield leppington.
stations , car parks @ edmondson park , leppington.
a new train stabling facility west of leppington capacity 20 8-car trains.
stage 2 received planning approval on 18 november 2010. on 7 december 2010, premier kristina keneally announced contract design , construction of stage 2 had been awarded john holland group.
on 13 september 2014, nsw government announced construction complete, saying line had come in $300 million under budget , year ahead of schedule. line opened 8 february 2015.
Comments
Post a Comment